Activity cost in SO Costing

Former Member
0 Kudos

Hi,

In our VC scenario, we have a sales order of 9 qty.

During SO Costing , the cost of components is picking correctly ie, cost of base qty * 9

But for the activity type why the costing is picking for base value of qty :1

I am not much more sure about costing part. Kindly guide.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Can I have any suggestion pls.

Thanks,

ajaycwa1981
Active Contributor
0 Kudos

Hi

check the formula assigned in Work center.. It might be a fix formula...

you need to include base qty and op qty in your formula to make it variable

br, Ajay M

Former Member
0 Kudos

Hi Ajay,

I have already checked.

It is maintain as

machine/base qty * operation qty