No budgeting without cost plan

Hi,

My client has a requirement wherein no budgeting should be allowed if there is no cost plan,

I tried to explore the user status functionality but there is no business transaction for cost planning which can have restricitve effect on budgeting.

Kindly help me to address the issue.

Thanks and Regards

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    May 23, 2012 at 10:20 AM

    hi,

    Search for User Exit for the same............

    Regards

    Sadiq

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Yeah you are right, user status for cost planning can not be set automatically. Rather you can try BADI WORKBREAKDOWN_UPDATE where update the status of WBS after cost planning.