Hi Experts,
I'm facing one issue regarding difference of dates in MD04 & RRP3 in APO.
There are few process orders for which APO is taking different dates, in actual, APO is calculating weekend days also which it normally does not (& which is not expected). This is happening only for a particular plant only. I tried doing CCR activity for the material-plant, but could not have common (correct) date in APO.
We have only gATP part of APO implemented. MRP & planning takes place in R/3.
I have verified factory calendars in R/3 & APO, and both are matching. Also checked Shipping calendar of plant (Shipping, planning, production calendars are same for this plant in /SAPAPO/LOC3), and shipping calendar also not showing weekend days in the bucket.
Also, this is happening only for Process orders, Sales orders are replicated with proper dates in RRP3.
Could you please advise if there are separate settings for this? Or how should I go about to solve it?
Many thanks !!!
AP.