HI all,  I Have created an investment project with 4 level of WBS, at 4th level WBS i have added the Budget and total up to 1st level, now my actual costs are at 4th level WBS and i need to settle it to 3rd level, then i will settle it to AUC.  But when i run CJ88 and put the 4th level WBS(i have already maintained settlement rule), the system is giving error that your 3rd level WBS is not have sefficiant budget.  Pls help me to solve this problem.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    May 22, 2012 at 10:12 AM

    Mandar,

    You should always give the background of your configuration.

    What budget plan you have? Is it overall or annual?

    At what level you are creating AUC?

    Regards,

    Amaresh Makal