Time booking for internal employee as well as employees of vendors for project

Hi All,

I have a scenario where project team (both internal employee as well as employees of vendors) booked time in Primavera. Now using middleware I want to capture the time in SAP PS. Pl guide now how to capture time in SAP PS where I can have distinction of internal/external employee time booked on same project.

Thanks in advance! 😊

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 21, 2012 at 09:46 AM

    Hi Rahul,

    You can define them as external employees in HR. WIth reference to suppplier Purchase order reference, you can book the timesheet for the external employees.

    Regards,

    Mahendra