Time booking for internal employee as well as employees of vendors for project

Former Member
0 Kudos

 

Hi All,

I have a scenario where project team (both internal employee as well as employees of vendors) booked time in Primavera. Now using middleware I want to capture the time in SAP PS. Pl guide now how to capture time in SAP PS where I can have distinction of internal/external employee time booked on same project.

Thanks in advance!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rahul,

You can define them as external employees in HR. WIth reference to suppplier Purchase order reference, you can book the timesheet for the external employees.

Regards,

Mahendra

Former Member
0 Kudos

Hi,

Thank you my mentor ! But is it possible to have stepwise guide to do that? Any document or any linkage will also work. I need to do it right from project creation, though that part is over.

Former Member
0 Kudos

Hi,

As Mahendra stated, please ask your HR team to enroll exernal employees in HR master data. Using their employee number and profile attached to them they can record their time in CAT2.

Do you have work instrucitons document describing the step by step procedure for internal employees? if yes, then just add a note highlighting the same procedure for external employees also.

Regards,

Sudhakar

Former Member
0 Kudos

Hi Sudhakar,

Thanks but I don't have any work instruction doc for internal employee either. Ya, here problem is I have to do HR role also else Mahendra n ur's solution is comprehensive in itself. Pl share if have something.

Former Member
0 Kudos

Hi Rahul,

I am not sure whether any such kind of document available in PS forum. Why don't you try to develop work instrucitons document which would help you to understand better and give more insight into what is happening. Delvelop you document and post here so that I will certainly review and try to help to fix whatever may be required.

Regards,

Sudhakar.

Former Member
0 Kudos

Hi Sudhakar,

Thanks, will try to do that.

Former Member
0 Kudos

Hi Rahul,

I think following bullet points are useful for you to make sure document is having everything:

  • Creation of Operative Project Structure (Project > WBSE > Network > Activities)
  • Creation of HR Mini Master Data (make sure that Employee Personnel Number has IT=0315 - Timeshtee Parameters maintained) - Here you can defile EE Group and EE SubGroup for "External" Employee
  • CATS - Cross Application Time Sheet: Use CAT2 to record timesheet
  • CATA - To Transfer Timesheet to Individual component (actual confirmation of entered hours)

These are some of point which may be usefule for you.

Former Member
0 Kudos

Hi,

Thanks Swapnil. Will do it and update you.

Answers (0)