TMS QA Approval Process

Dear All,

We have planned to setup the TMS QA Approval procedure in our 4 system landscape and have setup UAT system as QA approval system. But we want to use the approval process till UAT.

Eg: We want to approve the request in SAP, before it is moved to QAS and then one more approval to UAT.

When we login to DEV with STMS_QA t-code, the requests which are waiting for the approval have a target system / client of UAT (QA Approval System). Is there any way with which we can control the approval process from DEV - QAS - UAT? We cannot use DEV as QA approval system as it is not a target of atleast one consolidation system.

Appreciate your help..

Thanks

KP

Screenprint.JPG (49.7 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    May 21, 2012 at 12:42 PM

    Hi Krishna,

    from my experience stms_qa is just possible for consolidation targets.

    Quick: "Approval" of putting requests into import queue of QA is the release of the TO. Imho one possible solution would be to restrict release authorizations to some central people.

    Sophisticated: Another possible approach is SAP transport workflow. Maybe this can be of some use for you (release of help page may not be fitting, but I suppose the approach is the same) :

    http://help.sap.com/saphelp_sm40/helpdata/en/c4/08fef0e2af11d2b41d00609419f767/frameset.htm

    Regards,

    Peter