Budget Availability Check at the Time of Material Reservation

Hi People,

We have a requirement to check budget availability at the time of Material Reservation.

The scenario is that when some material is required to be consumed through Plant and Maintenance, the responsible person

will first create the create the PM order (breakdown or maintenance). Then against this PM Order a reservation will get created

once the order is released.

So the requirement is that while creating the reservation itself the system should check the budget availability and then stop / allow

the user to create the reservation. Else even if the budget is exceeded the system will allow the user to keep creating reservations.

Any help or input in this regard will be useful to us.

Regards,

Dhruv

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 15, 2012 at 07:27 AM

    Hi,

    It's possible as of release 6.03. Please, read notes 1321375 and 1278967.

    Regards,


    Eli

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Eli,

      Thanks for your valuable inputs. You surely are "Lender at the Last Resort".

      Regards,

      Dhruv