Transfer Plan Data from CO to BCS only transferring 1 Month's Planning Value

analistia16
Participant
0 Kudos

Hi Experts,

My team is using FM BCS in the current implementation project and as for the budget deployment, we are going to use FMCYCOPI_CO transaction to transfer planning value from Cost Center to Fund Center.

When executing the transaction, everything seemed fine as no error was throwed. But when checking on the data, I realized that the program did not transfer the complete planning value.

I set the period "from" 1 "to" 12, but the program only transfer the planning value of the 1st month (January). Wasn't it supposed to transfer the annual value (total from month 1 to 12) ? And a while after that, I again executed the program for different fund center and I set the period into "from" 3 "to" 3. That time, the program transfered only the planning value of the 3rd month which was correct.

Does that mean I have to execute the transfer program one by one for each month? Or did I miss any configurations/ parameter settings when performing the transfer for annual values (month 1 - 12?)?

Thank you,

Appreciate your prompt responses.

1 ACCEPTED SOLUTION

iklovski
Active Contributor
0 Kudos

Hi,

No, no configuration is missing. It's a bug, which is solved by note 1546444.

Regards,


Eli

View solution in original post