Hi experts,
For STO's the lead time is taking times from the route definined in the condition type in GATP.
To be more precise. The transportation lanes are created from manufacturing location ( Delhi) to DC Distribution center (Mumbai) and the days mentioned in the T Lane is 5 days.
But the route times which i have in the condition type for transportation is 3 days. so when TLB is run, it creates stock transport orders and its taking route times but not considering transportation lane times. So in GATP transportation and shipment scheduling is there any config which overrides the route times and considers the transportation lane time for STO's.
Pls guide me the configs required.
Thank U
Shruthi s