Hi Sid,
I believe the problem is due to the way the recipe is configured. There isn't enough information in the screenshot to troubleshoot your exact issue. I can't tell which operation each phase is in.
You are not allowed to have more than one relationship per phase within an operation. For example, if phases 50, 55 and 60 are all within the same operation, you can't have End-Start for 50 to 60 and End-Start for 55 to 60. The relationships have to be changed or phase 60 has to be put in a different operation.
Best regards,
Mike