We are creating process order for FG 10000011.

When we clicked on  "detemine cost" icon, it gave error Messages were issued when costs were calculated (see log).

When we went into log, it showed followng error: Item 00006 : Cost element  does not exist in CO area D000 for 07.05.2012

Item 00006 is a scrap output with FG 10000011. Being scrap, it is non valuated material and hence there is no accounting and costing view.

 

Our issue is: Why its asking for cost element even if there is no valuation class. Its not specifying cost element name in the error.

Other information:

We tried same process for FG 10000007. This FG is also having OTHER scrap (as output). This scrap is also non valuated. But it does not give any error.

Please let me know what could be the issue.

Accepted Solutions (1)

Accepted Solutions (1)

former_member221515
Active Contributor
0 Kudos

Removed "Relevant to costing" tick from BOM. Error solved