Planned Delivery time in Purchase Request

Former Member
0 Kudos

Hi

As per SAP, If the Purchase Requsition is created through the MRP run,

The planned delivery time in Purchase Info record should be considered instead from material master.

But for my case, PR is still consideres from the material master.  What should be done to fix this ?

regards

MM

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

HI,

On the customizing transaction OPPQ, you can  set for your plant the
flag 'Scheduling Info Record/Agreement'. In this case, the planned
delivery time is read from the Info Record, rather than from the
material master.

You may create the plant-specific purchasing organization data for the
info record, setting a planned delivery time or either uncheck the
mentioned flag on OPPQ, to read the planned delivery time from material
master.

Please check question 3 of the following FAQ note for more details:

550014 - FAQ: Source determinatn in the material requiremnts planning

BR

Nadia Orlandi

Former Member
0 Kudos

hi Ajit/Swetha

Thanks for the infor.

OMDT already checked.

However still the PR created through MRP doesn't consider the PIR planned delivery time and still get from Material Master.

regards

MM

ajitkumar
Active Contributor
0 Kudos

i think it is also essential to have a source list for the material where in the vendor is entered as a source

JL23
Active Contributor
0 Kudos

Please read OSS Note 550014 - FAQ: Source determinatn
in the material requiremnts planning

Answer to Question 3 explains how the delivery time is detrmined

Former Member
0 Kudos

Hello,

No need to do any settings. Standard SAP will consider Planned delivery time maintained in Inforecord and it overrides anything maintained in Material master.

There is already a thread reported:

http://scn.sap.com/thread/1990748

If you are creating the PIR manually refer the below link:

http://wiki.sdn.sap.com/wiki/display/ERPSCM/Purchase+Requisition+-+Planned+delivery+time+and+Info+re...

Hope the information is helpful.

Regards

ajitkumar
Active Contributor
0 Kudos

you have to check mark in OMDT for scheduling