Guys,

when i enter availability check as no check and product allocation as first step. product allocation is working fine without any issues. But if i change availability check as first step and prod allocation as second step, then even product allocation is not working. The products created for testing are new ones without any stock and reciepts. is that cud be the reason? Pls let me know if i am wrong.

Regards

Shruths

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 07, 2012 at 01:09 AM

    Shruthi,

    But if i change availability check as first step and prod allocation as second step, then even product allocation is not working.

    What does that statement mean?  If you are only saying that you cannot get a confirmation, then that could mean that ATP IS working (not all ATP checks result in a confirmation, by design).

    Always start with the ATP proposal screen in the ERP system.  Look at each bit of data that exists there.  The answer is always almost obvious.  The Product check portion of the ATP check should work exactly as you have configured it to work.  If the ATP doesn't pass the product check portion, the Allocation check is irrelevant, the end result is no confirmation. 

    You have done the Product Check configuration, right?

    Best Regards,

    DB49