hihi, everybody..

I am working on a client issue of sales order quotation costing with no quantity structure and no work center.

Where is the price for Activity Type set in this situation??

The costing result shows costing by units for one material but costing by fixed amount for another material.

Is there somewhere in SD configuration where different costing approach is set for different materials??

I never took the SD course.

Thanks.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on May 06, 2012 at 10:38 PM

    dear,

    please try some settings in SPRO under the 'Accounting Assignmnet/Costing' :

    regards,


    co.jpg (87.4 kB)
    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Yes, I can see the assignment of cost center to the sales order can make the cost component split creates a specified cost approach for the activity price.

      But I am still confused by how the different materials pick up activity price without assignment to cost centers currently.

      Regards.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.