A schedule agreement has been created for qty 100 for a particular material. Suppose that the validity of the agreement is 2 months, and the material qty in delivery schedule has reached 200. If the user does not the quantity in the scheduling agreement, is there a check/config through which as soon as the material qty in delivery schedule exceeds the qty in agreement, it should throw an error.
in Se16 open table t100, check application area 06 and ME language EN, whether you get any message for this , if so you can make this an error in define attributes of system messages in OLME > environmental data
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In standard SAP the system will stop you from ordering more then the target quantity (ME38, ME84).
Also during goods receipt posting against this scheduling agreement, if the unlimited tolerance check is not set, you would receive an error saying that there is more entered then released. So there are multiple controls on the delivery quantity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.