I would like to enquire as to whether in cProjects there is a Mass Change or a change function to change the persons responsible similiar to the function 'mass change' in CJ20N?
Can the change be done for individual tasks as well as the whole project?
Hi,
As far as I know, there's not such an existing tool in SAP PPM.
Standard report "DPR_DX_PROJECT" is available, but only for creation or deletion.
So you will have to develop your own report for such an update.
BR
Matthias