Hi,

We are in implementation of PS module. Our Planning strategy is 40. Demand has been generated by WBS, when we run the MRP plant stocks are not considering, instead new purchase requisions are getting generated. As per our client requirement plant stock to be considered while we run the MRP.

What settings required in MRP / Planning Strategy configuration / Availabilty check control. Will planning strategy 21 (Make-to-order prod./ project) with requirement type KP in OPPS help in considering plant stocks or any other settings required ? .

Please help on this issue