on 05-03-2012 11:16 AM
Dear experts,
We have created a sales order which item category has the special stock indicator Q, so when we create a sales order we must assign a WBSE to the item.
I would like to know if is there any way of getting the cost (of the production of the material we have sold) as a planned cost in the WBSE?
Thanks in advanced,
Fortian
In OPSV I've marked the Appended indicator for the PP Production order. So once the production order is created the planned cost appears in the project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |