Dear experts,

We have created a sales order which item category has the special stock indicator Q, so when we create a sales order we must assign a WBSE to the item.

I would like to know if is there any way of getting the cost (of the production of the material we have sold) as a planned cost in the WBSE?

Thanks in advanced,

Fortian

Accepted Solutions (0)

Answers (1)

Answers (1)

fortian
Active Contributor
0 Kudos

In OPSV I've marked the Appended indicator for the PP Production order. So once the production order is created the planned cost appears in the project.