Hi, when creating a request for change or change document in 7.1, the search results for an ibase yield no results. I have maintained my logical components with the appropriate system roles in my maintenance project, selected my approval procedure in the charm document, as well as identified a Project in the charm document.

Still, there are no search results for my ibase. They are appearing just fine in IB52.

Anyone have an idea of what's going on?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 16, 2012 at 07:12 PM

    Hi,

    have you checked SAP Note 1705702?

    Best Regards,

    Raquel

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 26, 2012 at 10:13 AM

    Hi Christian

    I had the same issue as you, even after implementation of sap note 1705702 (thanks for suggesting Raquel!).

    The only way to see my IBase numbers was to leave the "Project" field empty (in change plannig part - upper right).

    If your issue is still there you could try that...

    Secifying a project is supposed to filter Ibases to concerned systems by the project. But there is something wrong with my project.

    regards, jean