Hello Freinds,

Is there a way we can change customers portion in mass. The new portion would have the same billing dates as of the old ones.

Regards

Charvi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    May 02, 2012 at 07:27 PM

    Hi Charvi,

    First you have to create the NEW Portion and MRU with the billing and meterring dates you want using E41B and E41H. Generate the schedule records then.

    After that you go to EL59P to create the Parameter group where you will provide the date from which the MRU will be changed for the selected consumers, the new MRU and the old MRU. You can create it in Dev Env.and save it in a TR and move the TR upto Prod system.

    In Prod Env you have to go to EL59 and enter the Parameter group you created and the list of consumers you want to shift from one MRU to another. Keep in mind no open MRO should be there against them. Execute and you are done.

    Hope you can follow it.

    Thanks,

    Arghya

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      To display the Regional Structure Group in Conn. Obj., There are settings in SPRO. Follow the path given below...SPRO ->Utilities-> Master Data->Conn. Obj.->Define Field Selection for Conn. Obj.. Execute and then select Reg. Struct. Grp. field as Input field and save it. Now u can make an entry for Reg Strct Grp. in Conn. Obj.

  • Feb 20, 2015 at 08:54 AM

    Hi,

    Is there an option by which we can change portions inside different MRU's in Bulk. I have created a new portion and need to migrate some of my existing MRU's to that portion.

    Thanks,

    Monis Shakeel