Different WBS for Materials and Production Orders

17 Views

Hi Team,

The scenario is BOM is released in stages and and the same is appended in network activities acordingly.

The requirement is client wants to have the cost planning and budgeting done for all materials in a separate WBS and Production order cost in a separate WBS and monitor the cost accordingly.

My Doubt is since BOM is attached to a WBS through Network activity, in MRP, requirement planning happens only to that particular WBS. Is it possible to assign different WBS to materials that has PR alone and original WBS to materials having Plan Order/Production Order. without manual change in PRs.

Thanks