Budget problem

Former Member
0 Kudos

HI all,

I am facing a issue of budget control, scenario is evertything is working fine in all projects for budget control(on release+overall basis), but in 1 project, system is not controlling budget though availability control is active on wbs elements. System is not performing budget check for wbs elements. Please share your ideas. I tried CJBW and CJBV, then also same issue.

Regards,

Shrikant Patil

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Try running CJEN first and then run CJBN and check.

Former Member
0 Kudos

this is done gokul...but still issue is tehre...

Former Member
0 Kudos

Check the budget profile that is assigned in the project. Also check, what is the activation type for availability control for this budget profile. Whether the availability control gets activated on budget allocation or on budget release. If the availability control gets activated on Release of the budget check whether the budget is released.

Former Member
0 Kudos

Everything is there Gokul...budget is released and control is on the same...

former_member195427
Active Contributor
0 Kudos

Hi,

   Please check your available control settings:

1. Tr. Group is"++ " there or not. if not, maintain it.And take "Action of AVAC " as "Error message"

2.Also, please ensure that you have maintained budget >0 on these wbs elements because system check AVAC on budget more than "0" value. Hence the budget should be atleast Rs.1

Regards

Ankur

Former Member
0 Kudos

Hi ankur...i have all the above settings in place...still issue is there....avaliability control is not getting triggered.

sunil_yadav2
Active Contributor
0 Kudos

Dear Shrikant,

Please try below steps for that project:

1. deactivate availabilty control: CJBW

2. Refresh data base: CJEN

3. Activate avialabilty control: CJBV

thanks

Sunil

Former Member
0 Kudos

hi sunil...i tried it couple of time...but not working....