Former Member
May 01, 2012 at 08:36 AM

Budget problem

31 Views

HI all,

I am facing a issue of budget control, scenario is evertything is working fine in all projects for budget control(on release+overall basis), but in 1 project, system is not controlling budget though availability control is active on wbs elements. System is not performing budget check for wbs elements. Please share your ideas. I tried CJBW and CJBV, then also same issue.

Regards,

Shrikant Patil