Hi,

I'm looking for a user exit/enhancement where I can change the date that is taken into consideration during an ATP check when creating an order in VA01.

Standard SAP uses the 'planned delivery date' (MARC-PLIFZ in material master) in case of an external procurement, but I need to change this to the 'total replenishment lead time' (MARC-WZEIT).

Does anyone have an idea which user-exit or enhancement is suitable to achieve this?

Thanks you for your help.

Best regards,

Zhou

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Apr 30, 2012 at 01:45 PM

    You can try with the following;

    EXIT_SAPLATPC_001 (include LXATPU01) and EXIT_SAPLATPC_002 (LXATPU02) in the enhancement ATP00001 (program SAPLXATP)

    Regards,

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.