Apr 30, 2012 at 11:59 AM

Availability check - external procurement

142 Views

Hi,

I'm looking for a user exit/enhancement where I can change the date that is taken into consideration during an ATP check when creating an order in VA01.

Standard SAP uses the 'planned delivery date' (MARC-PLIFZ in material master) in case of an external procurement, but I need to change this to the 'total replenishment lead time' (MARC-WZEIT).

Does anyone have an idea which user-exit or enhancement is suitable to achieve this?

Thanks you for your help.

Best regards,

Zhou