Skip to Content

RG1 should update 6.00AM to next day 6.00AM

Hi Gurus,

I need to update RG1 as follows.

1)From Production:- 30th April from 6.00AM to 1st May 6.00 AM finished goods produced should update RG1 in 30th April's date.

2)From Sales :- 30th April from 6.00AM to 1st May 6.00 AM finished goods Sold should update RG1 in 30th April's date.

How to achieve this???

Is there any date at the time of excise invoice creation which updates the register?

also can we control the same from GR from production(101 movt type)?

Reg,

Amol

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Apr 30, 2012 at 05:38 AM

    dear, you would set up a background job(s).

    regards,

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 30, 2012 at 06:39 AM

    This normally happens in manufacturing unit where they have a cushion of one or two days to close their month end sales. So during delivery creation, they have to ensure that the Actual GI Date is the last working day of that month. If it is going to be in bulk, then you can schedule the PGI in background via program WS_MONITOR_OUTB_DEL_GDSI with the required control.

    G. Lakshmipathi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.