Having an interesting issue where the requirements type 11 (Gross Requirements Planning) has a consumption mode of 1 - and a consumption indicator of 3.

I was looking at other systems inlcuding an IDES application and those settings are not set when the independent requirement is created via MD62. Can someone lead me in the right direction as to where that setting is in the SPRO configuration, since it should not be activated?

There is a screen shot of those settings attached.

Thanks for the assistance.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Apr 29, 2012 at 02:19 AM

    Ed,

    You seem to be confusing requirements type with MRP Strategy.

    Requirements type is linked to Requirements Class in OVZH. Requirements class is then configured in OVZG. MRP Strategy, on the other hand, is configured in OPPS.

    You can review your local Client 000 to see the 'as delivered by SAP' settings for these configurations

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.