Skip to Content
0
Former Member
Apr 28, 2012 at 10:25 PM

How to get a PR for bulk material having scheduling agreement with MRP typeVB

30 Views

Hi all,

I have a bulk material used in production. This we issue out to cost center.. This bulk material is having scheduling agrreement and defined in material master with MRP type ''re-order point planning with 1000 qty.

Now when i see MMBE stock is zero, but despite having re-order point , it didn't generate PR.

Question is does bulk material with VB and having scheduling agreement will generate PR automatically or we need to create a manual PR and Purchase order.

Thanks a lot in advance

LKP