PP order has finish date on non-work day and no warning.

349 Views

HI, I have the work center and the Plant having the factory calender where only Monday to Thursday as work days.

However, when MRP run, i could see some planned orders having finish date on a Friday ( I an doing backward schdeuling) and also when I convert this to PP order no message was given that I have my Finish date on a Non-Working day.

I am not able to understand the issue. If i move the date to Saturday - it gives a warning message however not for friday.

Factory calender setting: Work days only from Monday to thursday.

Plant and the work center are assigned with this calender.

What could be the reason for this.

R,

Sarvan.