Hi Guys,
During creation of project in builder, while adding WBS to project structure, the fields in Dates tab gets greyed out in some projects, and is editable in some projects. We need to have this dates in change mode, so that client wants to have the dates filled in and schedule WBS wise.
Can anyone help why this happens and how to rectify this. Thanks in advance
Regards,
AM
Murthy,
Have you noticed the system status of the superior WBS elements under which you are creating new WBS elements?
Regards,
Amaresh Makal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi murthy,
check for which project profile (project definition) and project type (wbs) dates fields is not editable and then then check the config settings.
if the user are different then it is the authorization problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Murthy,
It seems like authorization issue here. Please check if you have the activity 20 (Create actual dates) authorization be assigned to the objects C_PRPS_KOK, C_PRPS_PRC, C_PRPS_VNR, C_PRPS_ART for the user.
Thank you & regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.