Dates in WBS in Project Builder

former_member513364
Participant
0 Kudos

Hi Guys,

During creation of project in builder, while adding WBS to project structure, the fields in Dates tab gets greyed out in some projects, and is editable in some projects. We need to have this dates in change mode, so that client wants to have the dates filled in and schedule WBS wise.

Can anyone help why this happens and how to rectify this. Thanks in advance

Regards,

AM

Accepted Solutions (1)

Accepted Solutions (1)

Makal
Active Contributor
0 Kudos

Murthy,

Have you noticed the system status of the superior WBS elements under which you are creating new WBS elements?

Regards,

Amaresh Makal

former_member513364
Participant
0 Kudos

Hi Amaresh,

Thanks. During creation of project using builder, the dates are greyed out. After finishing the structure and relase the project, the dates are in editable mode.

Rgds,

AM

Makal
Active Contributor
0 Kudos

Good Murthy. Has your problem been addressed ? If so, please close the thread.

Regards,

Amaresh Makal

Answers (2)

Answers (2)

0 Kudos

hi murthy,

check for which project profile (project definition) and project type (wbs) dates fields is not editable and then then check the config settings.

if the user are different then it is the authorization problem.

Former Member
0 Kudos

Hello Murthy,

It seems like authorization issue here. Please check if you have the activity 20 (Create actual dates) authorization be assigned to the objects C_PRPS_KOK, C_PRPS_PRC, C_PRPS_VNR, C_PRPS_ART for the user.

Thank you & regards, Gordon