In our SNP planning books, all of suddent we see Preqs getting creatred in the Distribution Receipt (Planned) Key figure) within the stock transfer horizon (7 days), the view is a daily view. FYI, we are using heuristics and alsoin SNP tab, the fix stock transfer setting is NOT checked. Funny thing is, when I run location heuristics interactively, even then it creates Preqs within the 7 days.

Is there any other program or setting that could create these Preqs within the Stock trsnfr Horizon? We dont want Preqs to be created within 7 days.

Thanks

Tej

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Apr 26, 2012 at 07:51 PM

    Hi Tej,       Based on your explanation I am visualizing following scenario. Someone might have ran SNP heurisitc without stk transfer horizon. System has created planned distribution reciepts. Afterwards they have been firmed. Later you might have set the Stk transfer horizon and ran SNP heurisitc again. As you explained you see them within stk transfer horizon and don't get deleted. This is my guess    Thanks Dev

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 26, 2012 at 02:31 PM

    Are you sure the stock transfers were created by SNP. Could some user have gone in and manually created those reqs ?

    Thats the only possibility i can think of . Because even if you had run heuristics and created the stock transfer before setting the stock transfer horizon, the subsequent heuristic run(after setting the horizon) would have got rid of the unfixed reqs within that period .

    Thanks

    Aparna

    Add comment
    10|10000 characters needed characters exceeded

    • Thanks for providing details patiently.

      Few more questions:

      • What is the release and package level of your production system?
      • Is your active planning version considers SNP stock transfer horizon of source ?
        • Pl check t.code /SAPAPO/MVM and SNP section
        • Source location has a different stock horizon and it's reflected in the planning (valid only if vendor also modeled in the system).
      • Can you update the stock transfer horizon and rerun the heuristics?
        • You need to come out of planning book, update the location product master, and then use the planning book to run heuristics. Please select only one location product (with single source, if valid).
  • avatar image
    Former Member
    May 02, 2012 at 09:11 AM

    HI All,

    Has this issue been solved already? Could anybody tell me what has been the cause on this issue? I am encountering the same right now and can't find any helpful posts.

    Thanks so much for you kindness!

    Regards,
    Kris

    Add comment
    10|10000 characters needed characters exceeded