Sales order confirmed before supply of components arrive

Hi,

I have an issue to consult on how can I can troubleshoot for the below issue.

1. SO confirmed 4/30

2. But PurReq to purchase part for the build only due 5/3

What factors could caused this? How I can troubleshoot?

Appreciate any advice, thanks.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Apr 26, 2012 at 07:33 AM

    Hi,

    You can check ATP for this sales order.

    If ATP is off for this sales order, then any quantity can be confirmed.

    If ATP is on, then verify ATP situation (Go into transaction VA02/VA03, click on "Environment" in the meau bar, then click on "availablity"). Also, please check ATP checking scope to verify whether other receipts elements has been involved to confirm the sales order.

    Claire

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      That meands "SNP: PReq" is considered in ATP check. the checkbox specifies whether the category is relevant for an ATP check on both location and sublocation levels. You can refer F1 help document. You can change your checking scope in transaction /SAPAPO/ATPC04_05.

      Claire

  • Apr 26, 2012 at 02:20 PM

    This is something to do with the bucket strategy that has been defined for your ATP group.

    Basically - in the ATP tab, if the Scope of check is saying that you are considering the above mentioned reciept element as available supply - then try to see the Bucket. Is it Progressive / Conservative / something else which is making it to be available before it is actually available.

    Also, you should check one more thing. What is the setting of Checking Horizon ? Is it configured in a such a way that the Material availability date that falls on or beyond the checking horizon is getting confirmed completely ? If yes, that explains the situation.

    Please let us know if it has resolved the problem or give more details to trouble shoot. How about attaching the screenshots while explaining the problem ??

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      I can see you are using setting "confirm at checking horizon". With this setting, all requirements can be confirmed at the end of the checking horizon. To aviod overconfirmation, you may change to use setting "no checking horizon" or " End check without confirming in the checking horizon"and recheck ATP for the sales order.

      Also, changing to use "Conservative" logic can make the order be confirmed at the end of ATP bucket.

      Claire

  • Apr 30, 2012 at 09:03 PM

    Hi Hock,

    Based on your explanation it looks like your sales order has confirmed the availability. I am assuming you confirm all the orders within few days.

    The purchase requisition is planned based on the procurement lead times. The purchase requisition due 5/3 is based on the procurement lead times you have defined. Please check your lead times.

    Thanks

    Dev