COMAC Availability Check Logic

Hi Experts,

I run COMAC on multiple order sharing the same component.

"Requirement date" of this component is also same.

On what basis COMAC will allocate the component to the Production order & show the missing part ?

For Example:

Assume Total Available Stock = 12.000

Order Pegged COmponent Reqmt Dt. Time Req'd Missing Part Reqmts qty. 1 X C1 01.05.2012 07:00:00 3.00 2 X C1 01.05.2012 07:00:00 3.00 3 X C1 01.05.2012 07:00:00 X 3.00 4 X C1 01.05.2012 07:00:00 X 3.00 5 X C1 01.05.2012 14:00:00 3.00 6 X C1 01.05.2012 15:00:00 3.00 7 X C1 10.05.2012 07:00:00 X 3.00

In above example we can see that material availability check as shown missing part against order: 3,4 & 7.

If requirement date is same for all the orders & if SAP then check the requirement time then qty. should be allocated to order 1,2,3,4 & 5,6,7 should come under missing part.

So, if requirement date is same what will be the next immediate column SAP would check?

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Apr 25, 2012 at 07:22 AM

    system will sort out the order based on the Basic Start date of the order and time in COMAC

    IThe basic start date of the 3,4, 7 is lies after 1,2.5,6

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.