TO creation after release of Process Order

Former Member
0 Kudos

Hi Experts,

How to create TO(Transfer Order) after the withdrawl of material i.e after the release of process order.

Regards,

Rock

Accepted Solutions (1)

Accepted Solutions (1)

former_member196530
Active Contributor
0 Kudos

Dear

There are two set up required for WM-PP for getting TO and TR :

1.Goto Define Production Scheduling Profile -in CORY OR OPKP .Slect the scheduling profile and goto Transport tab  .Here you keep the WM request option as 1-TR on release on Process Order or Production Order .

2.In OMKO for PP-WM intregration , Maintain Production Supply Area /General Tab -Production View ( Same Production Scheduling Profile ) and Warehoue Management View ( WH no and Storage Type ) .

3.Mainatain the same Production Supply Area in MRP2 view of the material .

Thanks

JH

Former Member
0 Kudos

Hi JH,

Please can you expalin in detail what setting we have to do in OMKO:

Because In OMKO i am just able to see the fields of Account assignment group & others.

So where to maintain production supply area ?

Please help me out.

Regards,

former_member196530
Active Contributor
0 Kudos

Dear Rock ,

Goto Logistic Exceution -Warehouse Management -Interface -Define Production-Production Supply Area .Here you have to maintain PSA .You have to also maintain General Control Data Tab -PP intregraion (Assign Production Scheduling Profile Here ) and  Ware House Management and Storage Type .

Same Production Supply Area you have also maintained in MRP2 viiew or BOM Item Details Screen or Work Centre .Prefernece of PSA determination will be Work Centre Default Supply Area (CR02-WC-Default Tab -PSA)  , BOM , Material Master

Hope this is clear

Revert for farther help

Regards

JH

sjeevan
Active Contributor
0 Kudos

Rock D'Mello wrote:

Hi JH,

Please can you expalin in detail what setting we have to do in OMKO:

Because In OMKO i am just able to see the fields of Account assignment group & others.

So where to maintain production supply area ?

Please help me out.

Regards,

It's not OMKO it's OMK0

For replenishment Movement Type for the warehouse and storage type 100 (if it doesn't exist for your warehouse copy from warehouse 001, in OMLJ) assign movment type 319

Push button general enter plant and storage locations and select release parts

Push button PP-PI select appropriate scheduling profile and for WM request make it = 1 (Transfer requirement and transfer order on release)

Push button Whse Number and check the box PP interface active

In tcode OMLJ copy all the movement types from warehouse 001 to your warehouse (especially 319)

In OMKZ enter your warehouse number and Auto TO =1 and check the box AddId

You'd have stock removal and putaway strategies in material master for the material.

Answers (2)

Answers (2)

anup_patil3
Active Contributor
0 Kudos

Hello D'Mello,

Did you checked & maintained "Production Scheduling Profile" setting for this requirement..?

Goto Tcode-CORY and in Transport tab, select WM Request as "Transfer Reqmt & transfer order on release".

Also, a transfer requirement/order can only be created, if

  • A storage location is maintained for the component.
  • The storage location is maintained as WM active.

Hope this will help.

Regards,

Anup

Former Member
0 Kudos

Hi Anup,

Thank's a lot.

The Config setting required for Generating of a TR & TO after the release of Process Order the setting in CORY is enough ?

Regards,

anup_patil3
Active Contributor
0 Kudos

Hello D'Mello,

Off-course; along side above PP-PI config, there must be important WM config done in SAP.. 🙂

Like, you need to make sure that a plant in which you're working should be Inventory & Warehouse Managed. Automatic To creation settings also must be maintained (Tcode-OMKZ).

Also the material/component should have WM view maintained with relevant data.

Check with WM person if anything important required to be done.

Regards,

Anup

Former Member
0 Kudos

Hi Atul,

Where we do maintain Plant as both Inventory & Warehouse managed.

Please provide the path.

Regards,

anup_patil3
Active Contributor
0 Kudos

Hi D'Mello,

You need to define this in Organization/Enterprise Structure.

For WM, need to define Warehouse Number and assign it to respective Plant in SPRO --> Enterprise Structure --> Definition / Assignment --> Logistics Execution.

Hope this will help. Also talk to your MM/WM consultant for more info.

Regards,

Anup

Former Member
0 Kudos

Hi,

You can use special procurement key '40 - Stock transfer from another plant' in the material master MRP2 view to run this scenario.

When you do run MRP for this material, system creates Purchase req in the main plant.

Convert this into stock transfer purchase order and receive the material from another plant.

Kindly refer previous SDN forum for material master and configuartion settings.

Former Member
0 Kudos

Hi Mani,

My requirement is to create Transfer order after the release of Process order.

I want this TO to get printed & material should get issued according to TO printout.

So after it the material should get issued from system using mov type 261.

Please put your views.

Regards,