Process Version confilcts using different NWDI tracks

Hi,

we have a set of Processes in a NWDI Track running in our productive environment (CE 7.2). Now we want to create a new release of the application, that means

the current track will be used as a maintenance track and a new track for the new release will be created for the further development.

The new track will be filled by forwarding the content from the existing track.

At the end of the developmenet, the new track will replace the application in the productive environment. We have to ensure, that alle process instances which have been started with the processes of the old track will still run after the transport of the (same processes) within an other track.

I checked the process repository in the NWA and i saw that the process version contains the NWDI-Track-Name.

Are we getting into trouble be replacing a active process version from track a with a new version from Track B?

Has anyone experience with that?

A alternative solution could be, to forward the new Track B after end of development to the maintenance Track A to get the application into production, but that is not our favored solution.

Best regards

Frank

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Apr 24, 2012 at 11:17 AM

    Hi Frank,

    it will not cause issues if you deploy the same process model from two different tracks. The track name in the process repository is only there for displaying purposes. The relevant information on the one hand side is the build timestamp (version column) and the deployment timestamp. The version of the process model that has been deployed at last will be automatically the active version. This one will then be used for new process instances. You can change the active version manually in the process repository by chossing "Activate" on a specific version.

    Best regards,
    Stefan

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 24, 2012 at 05:05 PM
    we are doing the same, no issue is found so far. but you have to make sure the approval UI in new track can still work with your old process definition.
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.