In consignment PO price should come from info record

Hi,

When we create a consignment PO with material & item categaory K,PO
price is showing zero value & that field is not editable(It is the
standard SAP behavior)

As a business need we want PO price should be fetch from consignment
info record & should be display in PO.
How it will be mapped ? Kindly suggest.

Thanks,
Amit Karanjkar

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • Best Answer
    Posted on Apr 24, 2012 at 07:05 AM

    Hi,

    Yes, it is standard as item catagory K with purcahse order!

    In consignment process, the consignment info record need to active in t.code: OMEV and then maintained consignment info record with tax code and price with other details, and then price will take from consignment info record only during posting.

    Regards,

    Biju K

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Bijay Kumar Barik

      Hi Bijay,

      Thanks for your reply.

      As you suggested for contract option my requirement will meet.To check same scenario I have created

      Info record

      Consignment Contract with Item category K - ( Type MK)

      Source list

      But while creating PR with reference to contract, PR is not adopting contract..is there any setting required to createPR with reference to contract ?? .Pls suggest.

      Thanks,

      Amit Karanjkar

  • author's profile photo Former Member
    Former Member
    Posted on Apr 24, 2012 at 08:01 AM

    Hi,

    Its standard behavior of the system.

    As per the SAP standard functionality , when using item category K , you cannot maintain the price in the PO as you are not exactly procuring the material from the Vendor . It will be just kept in your storage location but will still belong to Vendor until you make goods issue or withdraw in your own stock .till the time Consignment material is non valuated

    Thanks.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 24, 2012 at 09:29 AM

    Hi Amit,

    when u r creating consignment info record, please be careful, due to created of Info select info category 2 for consignment. date field should check carefully. PO date should not earlier than info rec date. any other issue let me know in details.

    Regards,

    Sanjeet Kumar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 24, 2012 at 08:28 PM

    Amit,

    SAP is designed in such a way that the price in the consignment info record is used only for the settlement of consumed stock with the vendor in MRKO.

    Mathew

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 25, 2012 at 05:33 AM

    Hi,

    This is a standard behaviour,the price for the consignment p.o shouild come from the Purchase info record.

    For consignment procurement. The following are mandatory

    1.Material and vendor master record.

    2.a.Cosinment Info record (Purchase info record).

    b.In consignment info record Price and Tax code is mandatory.

    3.So the price automatically come to the P.O.

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello Amit,

      As a standard SAP function, you can not have Price details in PO for Consignment process...

      You will see it only during settlement/invoicing (Tcode-MRKO).

      But still if you want to see the price as a business requirement, you need to look for some exit/development object. There's no other option... :-)

      Regards,

      Anup

  • author's profile photo Former Member
    Former Member
    Posted on Apr 25, 2012 at 06:51 AM

    As you know its not standard, so what are the work arounds

    Option1:

    - Create normal PO with consignment price which is same as consignment info record price, receive the stock and later transfer the stock to consignment using 412 K.

    Option2:


    - even in consignment PO, you can see the header conditions. you create a new condition specially for consignment and enter the consignment price as the header price. This price is just statistical price and it doesnt have any impact on account postings or any other transactions. or you may need to add a custom field in header / item level to display the price. this price can be used by the approvers for approval and this price can be pulled to PO output with additional logic in smartform. or if you want to display the PO price only in PO output, add the logic in smartofrm to pull the price from inforecord.

    Option3:

    If this price is only for approval purpose, approver can display the price in ME24N using environment-inforecord display option.

    For any case, consignment inforecord is mandatory and system considers inforecord price for all account postings.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.