on 04-23-2012 7:17 AM
Hi all,
I have maintained a material master record with plant specific material status. The plat specific material status is customized "L" = "STOCK".
When I maintain source list or create PR, I receive this warning message:
-------------------------------------------------
Message no. ME054
External procurement has not been defined for the material status of the material master record you entered.
------------------------------------------------
May I know if there will be impact?
Thanks.
Hi,
In MRP view, is this material allowed for External procurement?
Regards,
Devi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check field "Plant-sp.matl status" in Purchasing view of Material Master it should be blank if you do not want to block material
01 Blocked for procment/whse
02 Blocked for task list/BOM
IN Insuranace item block
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You've set the purchasing message as warning in OMS4 for status - stock. Thats the reason for this warning. This warning message doesn't have any impact in any purchasing transaction. you just ignore and proceed with all the purchase transaction.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check in OMS4 how the custom message is managed in different areas like purchasing, production, MRP, Inventory etc. A is warning and B is error
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.