Connecting the Systems after the OS/DB Migration in Solution Manager

Dear All,


I have completed the migration of DEV, QAS, PRD systems. Now I need to connect these systems to solution manager system. But in SMSY old systems are there with the same name like DEV, QAS, PRD.
Now If I want to add new migrated systems in the SMSY it says system is already there. So now I have two options
1) Either I need to delete existing systems (or)
2) Modify the existing systems to point new ip address and host names.
If I want to delete the existing systems first I need to delete the system assignments from logical components for those systems. But the logical components are getting used in CHARM, customer is saying he don’t want delete and reconfigure CHARM.
So I want to change existing systems the ipaddress and host name and those are in disable mode.
I would like to request any one can help me how to proceed in this situation?


Thanks & Regards,
Ravikiran Ch

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Apr 23, 2012 at 04:02 AM

    Hi,

    Which version of Solution Manager are you using? If its <=7.01, then you could manually update the details of the systems in the SMSY. There is an option 'Read System data Remote' in SMSY which should read the data from migrated systems.

    If version is 7.1, then SLD comes into the picture which would be lot easier from updating perspective. Delete old systems in the SLD and register new ones. The LMDB and SMSY in SolMan will read data automatically.

    Regards,

    Srikishan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Apr 22, 2012 at 02:50 PM

    Hi,

    change/adapt the existing RFC connections with the new/updated server IP address.

    Then update your data via "Refresh" in SMSY.

    Afterwards provide points pls...

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.