on 04-19-2012 1:43 PM
Hi
Am not aware of this basis activity of job schedules history maintenance and how it is done.
Can anyone help.
http://help.sap.com/saphelp_45b/helpdata/en/c4/3a7ede505211d189550000e829fbbd/content.htm
http://scn.sap.com/thread/403208
http://scn.sap.com/thread/1899017
I see the following jobs running on the system and the history is maintained only for 10 days.
SAP_REORG_JOBS
SAP_REORG_SPOOL
SAP_REORG_BATCHINPUT
SAP_REORG_ABAPDUMPS
SAP_COLLECTOR_FOR_JOBSTATISTIC
How can we increase this history details to say 2 weeks or 1 month if there is a requirement.
Is there any parameter - which will restrict the history to 10 days or would help to increase the time period to any desired level ?
Can anyone advise on this ?
Thanks
indu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Naor.
thank you very much.
In se38 : RSBTCDEL
As suggested i have created a new zvar1 for 15 days and used that variant for job : SAP_REORG_JOBS. Kept this for testing on a test server, so that we could do the same on production server.
Hope the same holds good for the spool delete as well : RSPO0041
Thanks again.
Regards
indu
Hello,
Best to use RSBTCDEL2
Note 784969 The RSBTCDEL2 program
regards,
John Feely
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi John.
Thank you very much for the info.
Shall go this the kbase. I am a bit confused. Because when i go thro the job, it talks only of the original program. Which is seen for the job.
So i presume that we have to create a new job with the new program and check the patch levels and sap notes etc and then do the necessary corrections for the jobs. Shall check on this.
thanks
Kind regards
indu
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.