Strategic maintenance plan call date with call horizon

Former Member
0 Kudos

Hello All,

We have Strategic maintenance plan with packages of 6W and call horizon is 50%. so I expect call date will be 3 weeks (21 Days) before the plan date.

But System gives the call date as 3 days (50% of weekly) before the plan date.

My Strategy is weekly unit, but I did not assign 1W package to my task list, I assign only 6W package, but sap consider 1W package and gives wrong call date.

Please help to fix it.