on 04-17-2012 6:13 PM
Dears,
it seems that it's possible applying surcharges on raw material cost estimates through MM condition types.
I did the customizing in my costing variant using a new MM contition type (%) and a new origin group.
I assigned the origin group to material masters, but nothing happened when i ran the cost calculation. I mean, costs were determined without additional surcharges.
Did I miss something?
Can somebody please confirm that my aim is achievable?
Thanks for your help,
Enrico
hi
please check to which the valuation variant for the plant, that may be having different strategy of sequence
krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
does it work only with some strategy of sequence? Which?
Is it correct saving the % of surcharge (MM condition type) trhrough Tcode MEK2?
Is the "release status" of the condition record relevant? Following the possible values:
BLANK > Released
1 > Blocked
2 > Released for pricing simulation
3 > Released for planning and pricing simulation
Thanks