Dears,

it seems that it's possible applying surcharges on raw material cost estimates through MM condition types.

I did the customizing in my costing variant using a new MM contition type (%) and a new origin group.

I assigned the origin group to material masters, but nothing happened when i ran the cost calculation. I mean, costs were determined without additional surcharges.

Did I miss something?

Can somebody please confirm that my aim is achievable?

Thanks for your help,

Enrico

Accepted Solutions (1)

Accepted Solutions (1)

venkatasatyakrishna_achan
Active Contributor
0 Kudos

hi

please check to which the valuation variant for the plant, that may be having different strategy of sequence

krishna

Former Member
0 Kudos

Hello,

does it work only with some strategy of sequence? Which?

Is it correct saving the % of surcharge (MM condition type) trhrough Tcode MEK2?

Is the "release status" of the condition record relevant? Following the possible values:

BLANK > Released

1 > Blocked

2 > Released for pricing simulation

3 > Released for planning and pricing simulation

Thanks