on 04-16-2012 12:04 PM
Hi all
We have COPA activated for our client and normally all sales order are settled to COPA. Now for a free goods / sample issue scenario i want the sales order to be settled to cost centre
Is this possible?
I tried to create a settlement rule with settlement optional to cost centre alone and made the default object as cost centre. But i get a error PSG not defined?
Where am i wrong?
Please help
Thanks
Hi Malathi,
Yes,you can settle sales order costs to cost center.create new settlement profiel and allocation structure with cost center as an optional and assign allocation structure in settlement profile.
Assign new settlement profile to item Requirement type/Class.
Thanks,
Rau
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Malathi,
Sales order settlement can be maintained through settlement profile, and see whether cost centers are allowed in the settlement profile.
Also check whether cost element is properly maintained in OKB9 for profitabilty segment.
Also check PA transfer structure is maintained and assignment for value field in KEI2
If you are accumulating settled cost in cost center, then you will be able to send values through asessment cycle in profitability segment.
Regards,
Kedar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.