on 04-16-2012 9:44 AM
Dear Experts,
I have two querries,
1) How to maintan alternata BUM for service master
2) Is it possible to create service order without service activity number but service Short Text ( like Text PO) and for that how to create service entry sheet?
Regards,
Channa
In service master we don't have option to maintain the alternate Unit of Measure as we have in Material Master.
There is no need of Alternate unit of measurement...
You can directly maintain the Base unit of measurement in the service master records ..ie. Hours etc (smallest one)...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Vikas,
we need a service activity as service charges, which may be used in BUm as Lumsum, Nos. KG, M2, SFT etc, it depends on the services. so my question here, is it possible to create one service activity with Alternate BUM for one activity instead of creating multiple service activities for each BUM.
Hi,
The error say clearly " Conditions for service price determination incomplete" means the condition type for service not defined in your Pricing procedure .
1st check vendor master which schema group of vendor assigned.Now chcek which Pricing procedure assigned to your schema group of vendor!
Just cross check Pricing procedure and you should have separate condition type for material and service.
Have your Pricing procedure and Keep both condition types for material and service( keep routine is 11 in Requirement) with following setting:
Count--Cond.Type--CondType Description--From-TO--Subtotal---Requirement--CalTy--BasTy--Acc--Ac
10-----PB00-------Gross Price-Material-----------------------------9------------------------------------------
20-----ZZ00-------Gross Price- Service------------------------------9--------------11-------------------------
Now create a fresh PO for service and see how condition types ZZ00 Gross Price- Service picks!
Regards,
Biju K
Dear Bijay Kumar,
I have checked the schema gp assigned to vendor nd pricing procedure. its fine.
If i create service order by giving the service activity number, its working fine and system picking the correct pricing procedure, but when I am trying to create service order without service activity number then system is throwing the error as "Conditions for service price determination incomplete". ( Here our requirment is to create the service order with service activity text but without service activity number i.e. like PO without material code. I am using Acc assignment "P" and item cat "D")
Regards,
Channa
pl check the service pricing procedure in SPRO> MM> External service management > conditons..for the valid pricing procedure there should be 2 conditions for total price. one automatic whose value will come from condtion table and other manual with a requiremement 5 or 6, which will get populated with the value entered in the PO service tab. probably you dont have the manual condition
Dear Bijay,
thanks for your reply,
We have two condition types for total price in ZMS000. PRS and ZPRS. we are maintaing condition price for activity in ML52 with Condition type ZPRS. kindly let me know how to create Service PO without service activity no. but with Service activity short text.
1) How to maintan alternata BUM for service master
In AC01, you can see the tab "intenal work" there you maintain the alternate UOM.
2) Is it possible to create service order without service activity number but service Short Text ( like Text PO) and for that how to create service entry sheet?
Service master is not mandatory to create PO. If you create service master or servic catalog, its easy for you enter the services or group together similar services(service catalog). But you can simply create a PO with item category D, and in the service tab just provide short text, qty and price. Difference between PO with service master and PO without service master, when you try to post service entry sheet, system wont pull the short text you entered in PO and you have enter manually once again in service entry sheet.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
I think you can ,but without service activity you can not create service entry sheet,you have to give all details there manually in ML81N
so better give all entries in PO itself
Kailas Ugale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1) Maintain it BUM through T-code AC02 or AC03,
2) Yes it is possible to create service order without service activity number but service Short Text, Service entry sheet will be created in same way
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
service ( item category D) PO can be created for text items. and SE sheet can be created in ML81N by calling the PO. its just like PO with service number except that there is no defaulting of certain data.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.