Dear all..

I have created one material with total self life.I know at the tim e of goods Receipt systam will force you to enter production date..

Im getting the Error to enter production date date, But where i have to enter production date.Im not finding production date tab in MIGO screen.

Batch indicator is not maintained..

please help me where i have to enter production date?

thanks

ramesh

Accepted Solutions (0)

Answers (3)

Answers (3)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

May be that field is hide for you, use t.code: OMJX  and make filed as Input field : GOITEM-VFDAT - SLED/BBD

Regards,

Biju K

Former Member
0 Kudos

If batch management is not active, you can see "date of manufacture" and "SLED" fields in item tab "material"..

- recheck the OMJ5 settings whether you activates the SLED check for that plant and activated SLED check with option 2 for movement type 101.

- Check in OMJJ / OMJX  whether field HSDAT in display mode.

Former Member
0 Kudos

Check in OMJ5 whether you activated SLED check for plant or movement type.

ramesh_reddy25
Participant
0 Kudos

Yes in OMJ5 SLED is activated for both plant and movement type.

ajitkumar
Active Contributor
0 Kudos