PS Standard Report Error.

59 Views

Sir ;

plz. suggest In CJI3 report Project Actual Cost Show Amount Rs. : 5,303,079.19/-

and In PS Report :S_ALR_87013558(Budget/Actual/Commitment/Rem.plan/Assg)

Actual Amount Show :10,606,158/- where our WBS Totall Budget :5,312,958/-

why in this Report Actual Amount Show Double if we compare this to CJI3 Actual Amount Rs.5,303,079.19/-.

Plz. provide solution to Correct this report.