Can we use a calendor for operation calculation in PPM.

Hi Experts,

Can we attach a calendor for duration calculation of opertaions in PPM's.

Which calendor does operations in PPM's use as reference while calculating duration for operation.

Awaiting for our reply.

Thanks,

Regards,

Srini

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Apr 12, 2012 at 11:49 AM

    Hi Sriini,

    The PPM's primary resource capacity requirements will be calculated based on the base and order quantities. This will be adjusted by the resource's active capacity variant (for instance capacity utilization, working hours, shifts, breaks, etc.). This further refined by a production calendar defined at the location level (t.code /SAPAPO/LOC3 and Calendars tab) during activities scheduling.

    Production calendar is based on a factory calendar and is represented as a continuous time stream. It is used to schedule production activities. A production calendar valid for the entire production is assigned to a location.

    Thanks,
    Rajesh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 12, 2012 at 12:33 PM

    Rajesh,

    For capacity consuming operations, you can affect the scheduling of the operation by changing the calendar assigned to the resource that is used in that operation.  /SAPAPO/RES01

    Assuming you are also integrating to ECC, you should also assign the same calendar to the Work Center Capacity in ECC.  CR02

    Best Regards,

    DB49

    Add comment
    10|10000 characters needed characters exceeded

    • DB49,

      Thanks for the elaboration. Since the active capacity variant includes the capacity profile based on the calendar associated with the resource, I have not explained it in detail in my response.

      Best regards,

      Rajesh