Dear Expert,
While uploading delta request from PSA , it has updated 70 % of packages to cube , remaining package failed due to BW System get down. Should i delete yellow status from Cube & start loading from PSA. Because large number records ( crores ) , first i have uploaded upto PSA only. In PSA request is fine.
Regards,
Anand Mehrotra.
Hi Anand,
Yes, it would be better if you delete the request and reconsctruct the entire data from PSA again