Enhancement for Ck11n or Ck40n

Former Member
0 Kudos

Dear ALL

I would like to Enhancement for Ck11n or Ck40n for where the system have exclude the cost estimate/ cost upload  process on those materials which material price is <= 1

Please advise.

Regards

Avijit

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member1108130
Participant
0 Kudos

Identify the materials that have Cost less than a dollar.

Do a mass update on Material Master(MM17). Update "Do Not Cost" Flag in Costing View 1.

Former Member
0 Kudos

Dear Nagu

yes...i know that, but due some problem I want to the said process through Uesr exist.

If I have use the enhancement COPCP005 instead of COPCP003 , is it correct process. Please advice (ref of Mr Ruzi) .

Regards

Avijit

former_member1108130
Participant
0 Kudos

You cannot use COPCP003 as it will not be called during std costing. In COPCP005 you cannot zero out the costs. You can make the cost a penny. SAP will not simply ignore a material that is on BOM, unless you want to check the "Not Relevant for costing" flag.

What is the exact business scenario. If say a Finished good FG1- has bom with two Raw Materials. RM1 ($10) and RM2 ($1). Cost will be $11. What do you want the cost to be?

Message was edited by: kala nagu

Former Member
0 Kudos

Dear mr nagu

Thank for reply..

Actually happened is our process is too large. MM team are create/edit Material code, PP team are creating BOM & costing team is executing the costing. More than 10 lacs FG, SFG (split valuated) & RW (split) are process. For this cause I have unable to search / edit / segregate the material value is low. So I want the user exist.

For your reply I want to exclude RM2 which is $1 with use option for "Not Relevant for costing" flag.

Because at future PP team it may update the value through MR21 without help of MM team.

Regards

Avijit

former_member1108130
Participant
0 Kudos

SInce you have many materials have an ABAP guy write a program to search for material where cost is less than $1 and update the "Do Not Cost" flag in material master.

0 Kudos

Did you try to check COPCP003?

The user enhancement COPCP003 (User Exit for Production Resource/Tool

Costing) enables you to include the planned costs for production

resources and tools in costing with quantity structure.