on 04-09-2012 9:06 PM
Hello Experts
Do you know which Badi/userexit I can use in order to change the plant calendary when the MRP create the "planned orders" ?
The objective is to use a special calendary (different then the plant one) to create the planned order with the MRP Launch
Thanks in advance
BR
Hello,
Please check BADI:
MD_CHANGE_CALENDAR BAdI: Change Calendar for Range of Coverage Calculation
Hope the information is useful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.