on 04-09-2012 9:03 AM
Hi Experts,
I am using scheduling functionality in my project. i am using forward scheduling, in forward scheduling we enter Basic start date and after scheduling system gives the Basic end date at network level. but in my case when i schedule my network, scheduling carried out but network header's Basic End date does not come. when i select my project definition then after network's Basic end date comes.
Please suggest me how can i get network's basic End date at network level scheduling.
thanks in advance
Hi,
Please check whether adjust basic dates check box is checked in Parameters for Network type for Network Type and Plant in your case.
Regards,
B p Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello Mr. Singh,
thanks for ur reply.
i am not able to find that basic dates chek in my configuration.
In configuration of scheduling my system contains-
Network scheduling parameters i selected "2 do not adjust basic dates,dep.requiremets to operation dates"
WBS scheduling parameters " basic dates check box is checked"
Now Please suggest me ...