Network Scheduling issue

former_member679976
Participant
0 Kudos

Hi Experts,

I am using scheduling functionality in my project. i am using forward scheduling, in forward scheduling we enter Basic start date and after scheduling system gives the Basic end date at network level. but in my case when i  schedule my network, scheduling carried out but network header's Basic End date does not come. when i select my project definition then after network's Basic end date comes.

Please suggest me how can i get network's basic End date at network level scheduling.

thanks in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

  Please check whether adjust basic dates check box is checked in Parameters for Network type for Network Type and Plant in your case.

Regards,

B p Singh

former_member679976
Participant
0 Kudos

hello Mr. Singh,

thanks for ur reply.

i am not able to find that basic dates chek in my configuration.

In configuration of scheduling my system contains-

Network scheduling parameters i selected "2 do not adjust basic dates,dep.requiremets to operation dates"

WBS scheduling parameters " basic dates check box is checked"

Now Please suggest me ...