Unable to create inspection lot during external process GR of a Production Order

Dear experts,

I created a production order with one of the operation set as external process which automatically creates PR and thus can be referenced for PO creation. I have maintained the QM view of the material master of the Finished Goods by using MM02. The QM view of the Finished Goods produced includes the inspection type 0130 Receiving Insp. From External Processing. After the PR was created by the system, I created PO based on the PR. Then, I carried out the GR of the external process by using MB01. Unfortunately, an error message appeared and the inspection lot of 0130 type couldn't be created. Please give the solution for this problem. Thanks in advance.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Apr 09, 2012 at 05:39 AM

    Hi,

    Please enter the inspection type to external operation parameters in production order operation detail view, then try again.

    Regards.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.